- Environmental Impact Assessment (EIA) procedure (2007-2008)
- Feasibility Studies covering five plant alternatives representing both BWR and PWR technology (2008-2009)
- Application for Decision-in-Principle (2009), including option for 1000 MW heat production for district heating
- Conceptual design development (2009-2010), including e.g. major licensing issues, engineering schedule and licensing plan
- Preparation of technical requirements for the call for bids (2009-2010)
- Development of project organization plan and management system for implementation (2009-2010)
- Site studies (2009-2010)